Hornsby-Quarry-banner.jpg

Edward Bennett Oval, Cherrybrook - Gross Pollutant Trap, Bio-filtration Basin & Stormwater Harvesting

Description of Works

The proposed works include installation of a Gross Pollutant Trap, bio-filtration basins and stormwater harvesting system. The aim of these works is to improve the ecological health of the natural water course by improving water quality and utilising stormwater for irrigating the oval.

The works are anticipated to start this financial year and take approximately 12 weeks to complete dependent on the weather.

Documents

Enquiries

  • Dinesh Tamang. Ph: 9847 6878 (Project Designer)
  • Kristy Hayden. Ph: 9847 6032 (Construction Team Leader)
  • Martin Drake. Ph: 9847 6886 (Design Team Leader)