Beecroft Village Green – Park Renewal
Council advises that renewal works at Beecroft Village Green are expected to commence on Monday 12 February 2024.
These works are in accordance with the Beecroft Village Green Master Plan adopted by Council in June 2023.
The project includes:
- construction of a new amenities (toilet) building
- new playground and fitness equipment
- new park furniture including a BBQ
- a half basketball court
- new pedestrian paths including an accessible path to the playground and picnic area
- signage and soft landscaping
Documents
- Beecroft Village Green Masterplan Final (PDF 1.1MB)
Enquiries
For enquiries please contact Zoe Cooke, Landscape Architect/Project Manager, Parks, Trees and Recreation on (02) 9847 6885.
April 2024 Update
Construction of the sandstone retaining walls has progressed throughout April and the playspace is now prepared and ready for installation of the new playground equipment.
Works are progressing on the new amenities (toilet) building with footings and the concrete slab scheduled to be poured early May.
March 2024 Update
Construction has commenced at Beecroft Village Green. Demolition of the existing playground equipment and toilet block are complete and sandstone retaining walls are under construction.
Temporary public toilets are located near the tennis courts for park users.